Sarnelli House Update
Parent Category: Charity Projects
Category: Sarnelli House
Greetings from Sarnelli House, Nongkhai!
I am very pleased to give you some updates on classroom and desks project.
Completed tasks: This coming Friday 15 Febuary we will pick up another 30 desks from Khonkaen and we will have in total 50 desks and 100 chairs for the children.
Records: Below is the record of finance and tasks. I keep everything by date. And I did order some desks in advance to set up a sample room at Nazareth House.Â
Â
No. | Date | Received | Spent | Balance | Details | Competed tasks |
10 desks ordered | ||||||
1 | 30-Nov-12 | 7,000 | Â | 7,000 | first tranfer for 50% of 10 desks | Â |
2 | 6-Dec-12 | Â | 7,000 | 0 | 50% of 10 desks | Â |
3 | 3-Jan-13 | Â | 7,000 | -7,000 | 50% of 10 desks | 10 desks |
4 | 9-Jan-13 | Â | 1,800 | -8,800 | 20 chairs | 10 desks with 20 chairs |
11 desks ordered | ||||||
5 | 10-Jan-13 | Â | 15,400 | -24,200 | 11 desks (finished) | 21 desks with 20 chairs |
6 | 10-Jan-13 | Â | 1,200 | -25,400 | Gasoline (pick up desks in Khonkean) | Â |
7 | 14-Jan-13 | 7,000 | Â | -18,400 | Second transfer for 50% of first 10 desks | Â |
40 desks ordered | ||||||
8 | 17-Jan-13 | Â | 20,000 | -38,400 | 40% of 40 desks (paid 20,000 of 56,000) remaining 36,000 | Â |
9 | 18-Jan-13 | 71,000 | Â | 32,600 | Third fransfer for 40% of remaining funds | Â |
10 | 31-Jan-13 | Â | 4,000 | 28,600 | Advance for painting task (paid 24,000 of 56,000) remaining 32,000 | Â |
11 | 2-Feb-13 | Â | 18,000 | 10,600 | 30% of 40 desks (paid 42,000 of 56,000) remaining 14,000 | 41 desks with 20 chairs |
12 | 12-Feb-13 | Â | 7,200 | 3,400 | 80 chairs (90 baht per chair) | 41 desks with 100 chairs |
13* | 15-Feb-13 | Â | 1,200 | 2,200 | Gasoline (pick up 30 desks in Khonkean) - 30 of 40 desks finished | 51 desks with 100 chairs |
 * It will be used when we pick up the 30 desks this coming Friday.
Room Renovation: We have only moved the two televisions out from the room and made one TV case. They have not set up lights and fans yet as the contractors had been engaged with some other tasks in the village. It will be done within this month.
Pictures: I send 6 pictures.
- 2 are some new tables at the carpenter's house.
- 2 are the classroom at Nazareth house with the kids. They have been using the desks everynight.
- 2 are the current classroom at Sarnelli House. We will put the new 30 desks for them this coming Friday.
Â
Funding: We will have 50 desks and 100 chairs completed this coming Friday. May I kindly ask you for the second payment (53,000 baht) sometimes after these task delivered. Thak you very much!
Â
Date of project completed: I foresee it will probably be at least the third week of March.
Â
Thank you once again for your continuing support and I truly appreciated to be able to meet the Spoofers two weeks ago. Have a great time gathering tonight! If there is any question please let me know. God bless!